Hurdles and Way Forward in Hydropower Development and Execution

Hurdles and Way Forward in Hydropower Development and Execution

The total theoretical potential of hydro power development is supposedly 83000 MW, of which 40,000 MW is considered to be techno-economically viable.  Per capita electricity consumption is only 60 KWh per annum and approximately 750 MW has been developed so far.

Though Nepal has this tremendous potential, it does not have good enough policies and execution strategy that would be helpful in the implementation of hydroelectric projects. The country has done a good job by starting with the privatization of the hydroelectricity sector in the generation process. Yet the contribution from private sector is too little too late.

 

This is due to many hurdles facing the promoters, and there are many ways forward to overcome such hurdlers only if they are seriously followed.

 

Er. Kiran Malla
Past President, Nepal Hydropower Association
Chairman
High Himalaya Hydro Construction Pvt. Ltd. (Class ‘A’)
Megatech Hydro & Infrastructure Pvt. Ltd. (Class ‘A’)
Union Hydropower Pvt. Ltd. (3 MW, Development)

HURDLES

 

  • Nepal Electricity Authority (NEA) stopped ‘take or pay’ Power Purchase Agreement (PPA) with private developers due to fear of spill energy in wet months (8 months April-November).
  • NEA’s employees appear to be paranoid about losing their jobs and the benefits that accompany such as retirement fund/gratuity etc because of PPA deals with private sector. Employees believe that PPA will ruin NEA and it is bleeding to death for them.
  • NEA has monopoly on transmission, trade and distribution.
  • Although NEA is a huge overstaffed organization it does not have proper incentive structures at lower and higher levels.
  • NEA is supposed to be an autonomous organization but is highly influenced politically. Board Members are politically appointed and numbers of trade unions exist, which, in general, act as regressive forces impeding the smooth and efficient functioning of the organization.
  • PPA is basically flawed in the sense that, while it undertakes to build transmission lines for the power generated to be connected to the regional grid upon completion of the project, it does not have any liability in case it fails to erect transmission lines in time causing huge financial losses the producers
  • Micro hydro and small hydro projects are expensive to build due to their remoteness and difficulties of transportation / access, erection / installation of transmission line, substation etc.
  • Bank’s interest rates are high and fluctuating so project cost also fluctuates.
  • Although the Bank is not a party to the Contract between the Power Producer and the Contractor the so-called Bank’s Consultants tend to raise unnecessary and impractical objections and queries on the bills certified by the Project’s Consultants thus delaying the payments to the Contractor, Delay in payments causes cash flow problems to the Contractor. This affects(delays) the progress of works at site, which in turn causes much greater financial loss to the Employer (power producer) in the end.
  • Fragile geological conditions, young Himalayas, floods and landslides are natural causes and hurdles for smooth construction of hydro projects.
  • Lengthy licensing process (survey to generation), land acquisition, tree cutting, forest and environment clearance etc for development and execution of projects are definitely policy hurdles for hydro development. Even it takes long time for the Government organisations for all type of clearances from different Ministries to implement projects.
  • Foreign construction companies are allowed to be involved in the construction of even small- and medium sized hydro projects. It is experienced that the final construction cost and time far exceeded the original contract amount and construction period. One of the main reasons for this is incomplete design and hence lack of construction drawings at the outset and too many late changes during construction period.
  • Government don’t provide guarantees to any foreign Exim Banks, Asian and European Banks for projects to be developed by private developers in Nepal.
  • Electricity tariff is not adjusted as per current scenarios to meet the cost of generation, transmission, distribution and future expansion.
  • Lack of qualified and experienced personnel and professionals in development and management of execution of projects.
  • No proper policy and Government support for licensing, development and execution of large size hydro projects for multinational foreign companies.
  • Local disturbances, unwanted demands, strikes, road blockage are certainly hurdles for construction of projects timely and efficiently.
  • Different Ministries / Departments (Energy, Finance, Forest, Local Development, Home, Defence, and Environment) are involved in hydro development and go-ahead from Ministries are time consuming. Thus, bureaucratic hurdles are inevitable in the  development and execution of project.
  • Transmission bottlenecks widely exist throughout the country. It is getting difficult to evacuate power produced from different projects all over the country.
  • Shortage of high dam hydro projects (storage projects) to cope with the peak demand and thus to match the daily demand of power / energy.
  • Exchange risks, Dollar PPA, PDA (Particular Development Agreement) of Projects are major concern of foreign developers.
  • Political instability is hampering badly in policy, development and implementation of projects. There is no unified agenda for economic development. Instead, all political parties have their own agenda and vested interests. Even major political parties have different agenda and interests depending on whether they are in power or out of it.  Nepal is still in a transitional phase.  Without political stability and strong implementation laws no economic development process can move forward.

WAY FORWARD

  • NEA should continue with ‘Take or Pay’ PPA with developers private or private/public partner. Only then bank finance is possible to go into execution of projects.  Real use and demand of available energy could be much higher than anticipated by NEA.  Electric energy obviously is used in all household requirements like cooking, heating, lightening, cleaning etc.  Big and small industries shall flourish in different parts of the country without any doubt.  Electrical engine driven transportation could be enhanced.  So fear of ‘Stop PPA’ should be replaced by ‘Take or Pay PPA’ immediately.
  • NEA’s employees should be secured by Government of Nepal for their continuation of employment, retirement fund, gratuity etc irrespective of payment of money flows from NEA against purchased energy from other parties.
  • Transmission and distribution authority could also be provided to other eligible and interested parties through proper arrangement of license.
  • NEA should be unbundled and political intervention stopped for smooth and efficient operation of NEA. Labour/Trade unions should act in a fair and reasonable manner, not greedily.
  • Large scale hydro projects like reservoirs should be prioritized for implementation by NEA to balance the daily demand including peak and off peak.
  • Country / NEA should also be focused to build transmission line network throughout the country and across the border as well.
  • Micro hydro and small hydro projects could be instrumental for rural electrification. Private developers / community people should be given sufficient incentives for such developments.
  • Tax holiday exists now. No ‘VAT’ on hydro projects should be the policy to encourage developers so that good benefit is secured due to reduction in production cost.
  • Real one-window policy should be implemented for licensing, land acquisition, forest / tree cutting, environmental clearance etc to all hydro projects so that there could not be any hindrance and project completion/implementation time shortens drastically. Ministry of Energy should have the authority to deal with and finalise all requirements for implementation of hydro projects as one-window policy through declaration of ‘Emergency Energy Production Policy’.
  • Nepalese construction companies must be involved in the construction of small and medium size up to 100 MW hydro projects to be developed by public / Government Company. Unnecessary financial and technical qualification criteria will sideline national construction companies.  Nepalese contractors should be encouraged from all aspects to build the nation.
  • Government should provide the guarantee for foreign investment such as investment by Asian Development Bank, Word Bank, IFC, Exim Banks, European Banks and Chinese Banks etc.
  • Tariffs should be adjusted to recover the cost of buyer like NEA and profit from private / public developers. It should be utilized for further investment in hydro projects, transmission line in the country.
  • Qualified and experienced persons should be given responsibility for the management of organisation and execution of projects in public sector. Private sector does their best by deploying very capable and experienced person in managerial and execution level of their organisation / projects.
  • Multinational companies could be provided long term license with all government facilities to build, own and operate large hydro projects and to export or establish factories / industries etc in country so that they could benefit and or use their product by themselves or they earn money by exporting of energy produced.
  • While political stability is a must all major power should work together to formulate right policy, create investment friendly environment, enact laws to reduce all social, local hindrances, political interventions /appointments in implementing authorities for development and smooth execution of hydro projects.

 

CONCULTIONS

Due to above facts and the real existing scenario of country it is very explicit that there are many hurdles and challenges for proper development and execution of hydro projects.  However, there are many opportunities and way forward actions / solutions to overcome those hurdles for economic development of country through constructing hydro projects.

 

All hydro projects are owned by country / Government sooner or later no matter who develop the projects.  So there is nothing wrong if private sectors are given incentives during their operation period.  Hydro projects should be on ‘BOOT’ basis for private developers.

 

 

We should mainly focus of hydro-electric power clean energy for utilization in household services, water supply, irrigation, flood control etc. thus making it a multi-function single resource for overall development of the country.  As modern human being we need energy 24 hours to meet our basic needs.  Importance should be given to train manpower (practical, theoretical, higher education) and retain those trained manpower in the country for development, management and execution of hydro projects.  Country needs all sizes of hydro projects from micro hydro to large size storage projects to meet the need of rural electrification, industrial, household and service sectors of nation.

Nepal’s own resources in public and private sector should be utilised fully by giving special incentives to both sectors for speedy execution of hydro projects.  Investment friendly environment must be created through proper policy and Government support for local and foreign private developers because local resources are not sufficient to cope with the expenses and expertise needed for hydro development.  National / Local contractors to be encouraged for construction of all hydro projects with the exception of  large or  storage type of projects.  There are good fleets of semiskilled, skilled manpower available in the country and many more ready to come to work in country from abroad once opportunities are made available to national contractors and consultants from beginning to the conclusion of projects.  As hydropower is the backbone of economic development, policy level improvements need to be strengthened for which political stability is also a must.  Special attraction and benefits should provided through PPA, tax holidays, incentives to local developers and builders so that there will be good inflow of money as an investment in construction of hydro projects to meet the energy need of nation and a way forward step to being an energy- independent country.